Mayflower Halls

Project Start: February 2014

Project Finish: September 2014

Location: Southampton

Description:  Scheme comprises construction of three buildings ranging in height from 9 storeys to 16 storeys to provide student accommodation (197 cluster flats – 1,104 study bedrooms) above ground floor commercial uses (1,152 square metres floorspace) with parking. A team of 15 to 30 CSCS carded operatives with a minimum of two SMSTS qualified supervisors attended site 6 days a week to complete the builders cleaning on the project

Project Size: £72 Million

Service Provided: Builders Cleaning, Sparkle Cleaning, Window, Cleaning Carpet Cleaning, Kitchen Deep Cleaning

Contractor: Osborne Construction